I.C.T Supports Kazakhstan Electricity Meter PCBA Production and Factory Setup

Building a new electronics manufacturing facility involves much more than installing machines. Production teams need to coordinate equipment, utilities, BOM data, production programs, fixtures, process parameters, inspection systems, and operator training before stable production can begin.
This was the situation for an electronics manufacturer in Kazakhstan producing electricity meters and related electronic products. The customer was establishing a new production facility covering SMT, DIP, PCBA inspection, final assembly, and functional testing.
I.C.T supported the customer throughout the production preparation stage, including equipment installation and commissioning, SMT/DIP process setup, BOM and CAD preparation, production programming, AOI debugging, wave soldering adjustment, and on-site operator training.
The goal was not simply to get the machines running, but to help the new factory move toward real production readiness.
Why This Meter Factory Needed More Than SMT Installation
The customer was building a new factory for electricity meter manufacturing. The project covered power board SMT assembly, meter mainboard SMT assembly, DIP insertion, wave soldering, AOI inspection, final meter assembly, and complete meter power-on testing.
This meant that the factory could not be evaluated by SMT placement alone. The production process had to connect PCB loading, solder paste printing, component placement, reflow, inspection, insertion, wave soldering, belt assembly, pneumatic pressing, testing, and customer-side production flow.
The equipment included an L330 loader, 4034 printer, C500 connection table, S1 placement machine, S8 reflow oven, V8 offline AOI, insertion line, W2 wave soldering machine, WU400 wave soldering loading and unloading equipment, 6-meter belt assembly line, and SA30 pneumatic press set. In this type of meter PCBA route, an automatic solder paste printing machine is only one part of the full production connection.
The customer also needed support for PCBA/BOM/CAD file handling, feeder station optimization, material classification, AOI program debugging, reflow testing, wave soldering parameter adjustment, and verification for both small-batch and batch production.
Key Problems Before Production
Factory Utilities Were Still Being Completed
At the beginning of the project, the workshop electrical system was still under installation. The three-phase power was a five-wire system, but the site initially did not have a neutral wire prepared for the production layout. Ventilation and fresh-air systems were also incomplete, and temporary exhaust ducts for the reflow oven and wave soldering machine were not sufficient, resulting in heavy smoke during production.
The compressor room was another issue. The space was enclosed and hot, which was not ideal for equipment heat dissipation. During operation, the compressor showed automatic shutdown and oil-leakage risk, so the air supply and compressed-air system had to be checked together with production readiness.
Product Data and Materials Were Not Ready for Programming
The customer’s BOM, CAD files, and material lists were mixed at the early stage. Some material names, specifications, part numbers, and third-party information could not be matched, which affected program creation and feeder-station confirmation.
During first production, some component directions could not be confirmed from the drawings. The team also found missing materials, wrong materials, component throwing, reversed direction, and feeder-related issues. These problems are common when a new factory moves from documentation to real production: the machine program may be ready, but the actual material system still needs correction.
DIP, Wave Soldering, and AOI Needed Separate Debugging
The DIP and wave soldering process presented its own difficulties. During mainboard DIP debugging, there were bridging and low-solder issues. The final analysis showed that fixture flatness, insert material stability, local protrusion, high-temperature material deformation, lack of cover plate protection, and insufficient insertion material tension all influenced the soldering result.
AOI also required preparation. At the early stage, after capturing the product-defined area, the system could not return to the main interface normally, and activation-related issues had to be resolved before inspection programming could continue.
How I.C.T Prepared the SMT, DIP, and Assembly Process

Equipment Installation and Utility Verification
I.C.T first checked the machines, random accessories, feeder condition, nozzle condition, and auxiliary materials. The team then installed and connected the printer, placement machine, reflow computer, display, mouse, keyboard, signal lights, and line communication interfaces.
The air compressor, storage tank, dryer, compressed-air piping, and power supply were checked and connected. The team also inspected the electrical cabinet, three-phase power, neutral wire, and ground wire. When unreliable switch wiring was found, it was reworked to support safer equipment operation.
After installation, the loader, printer, conveyor, placement machine, reflow oven, AOI, wave soldering equipment, insertion line, and belt assembly equipment were powered on and tested. The equipment commissioning and bare-board testing were confirmed as PASS.
Program Creation, Feeder Optimization, and Inspection Setup
For SMT production, the team created placement programs based on BOM and CAD files. Mixed materials were reclassified, files were merged, feeder stations were optimized, pickup positions were adjusted, component packages were edited, and nozzle configuration was prepared. For factories planning similar meter PCBA production, the placement stage must be matched with the real component package, feeder setup, and board design, whether the line uses a compact placement platform or a high-speed pick and place machine.
Because some BOM and CAD information was unclear, the customer and the material supplier were asked to provide documents categorized by mainboard, power board, structural parts, SMT materials, and DIP materials. This helped the customer build a cleaner material foundation for later batch production.
The team also completed AOI feedback handling and activation-related processing. AOI coordinates were imported, inspection programs were created, components were debugged, and false calls were optimized so inspection could support real production instead of remaining a standalone test. A reliable SMT AOI optical inspection process is especially important when the same factory must verify both mainboards and power boards.
Reflow, Wave Soldering, and Assembly Training
Reflow oven temperature tests and chain-speed adjustments were completed, and the customer was trained to set temperature curves according to solder paste TDS requirements. A lead-free hot-air reflow oven must be configured around the PCB, solder paste, component thermal sensitivity, and target production rhythm. For wave soldering, the team adjusted tin melting, spray, preheating temperature, conveyor speed, flux spray speed, spray width, and spray continuity.
The team also communicated fixture issues with the customer and the fixture supplier. They recommended improving fixture chamfer, flatness, hole opening, and cover plate design to reduce bridging, low solder, and insertion floating during DIP and wave soldering.
Finally, customer engineers were trained on loader, printer, placement machine, AOI, reflow oven, insertion line, wave soldering machine, plug-in line, and assembly line operation. A production process SOP for SMT and DIP workshop operation was also provided for future improvement and localized use.
FAT Results and Production Capacity

After installation, debugging, and training, the customer completed functional verification for the mainboard, power board, meter assembly, SMT process, DIP process, AOI inspection, and customer-side production steps.
| Area | Documented Result |
|---|---|
| Mainboard and power board testing | Electrical tests were completed and functions were normal. |
| Meter assembly testing | After complete meter assembly, power-on testing was completed and operation was normal. |
| Mainboard SMT production | 300 boards were produced during one verified run, with 100 boards tested and normal. |
| Power board production | 154 PCS were produced in one recorded run and met the customer’s production requirement. |
| Power board small-batch verification | 400 power boards were completed on the SMT line, followed by functional testing coordination. |
| AOI programming | Offline AOI programming and debugging were completed and passed assessment. |
| Customer acceptance | Loader, printer, conveyor, placement, AOI, insertion, wave soldering, assembly line, compressor set, and related equipment were accepted as PASS. |
The recorded production capacity also showed the customer’s process direction. For mainboard TOP-side production, the loader reached 240 PCS/H, the printer reached 480 PCS/H, the placement machine reached 48 PCS/H, and reflow reached 380 PCS/H. For power board TOP-side production, the printer reached 300 PCS/H, placement reached 60 PCS/H, and reflow reached 190 PCS/H.
In later SMT production, the mainboard TOP/BOT small-batch output reached 50 PCS, and another SMT mainboard production record showed 300 boards with AOI test boards reaching 200 boards. These results gave the customer a practical production foundation for electricity meter PCBA manufacturing and final product assembly.
This Kazakhstan project is different from the Algeria mobile motherboard PCBA production line case, which focused mainly on mobile motherboard SMT line setup and programming. It is also different from the Vietnam PCBA soldering quality improvement case, where the key value was improving selective soldering yield. This meter project required a broader connection between SMT, DIP, wave soldering, AOI, final assembly, and complete meter power-on testing.