I.C.T Reduces Solder Joint Voiding to 3% on an LED Strip SMT Line in Italy

I.C.T Reduces Solder Joint Voiding to 3% on an LED Strip SMT Line in Italy

In September 2026, I.C.T completed a three-week on-site engineering project for an Italian manufacturer of flexible LED strips. The project covered the installation, commissioning, testing, and handover of a new SMT production line, including production equipment for long PCBs up to 1500 mm and downstream LED strip assembly.

The machines were running. The line was installed. The customer team had been trained.

But one production problem remained.

The solder joint voiding rate on the LED strip product was still above the customer’s requirement. Over nine days, the I.C.T engineer carried out controlled testing across solder paste application, thermal profiles, vacuum conditions, conveyor speed, and flux volatilization.

After 19 different parameter combinations, the final production trial reached an average solder joint voiding rate of approximately 3% while keeping the peak temperature at 258 °C.

This was not simply an equipment installation project. It became a detailed process investigation into why a working vacuum reflow system was still producing excessive solder joint voiding.

Project Background: LED Strip SMT Production

The customer was establishing a new SMT production process for flexible LED strips and long PCB products.

The production flow included:

PCB Loading → Solder Paste Printing → Component Placement → Reflow Soldering → Unloading → LED Strip Assembly

The line needed to support long boards while maintaining stable transfer and process conditions.

For manufacturers establishing a complete SMT production line, board dimensions, product data, printing requirements, placement parameters, reflow conditions, and downstream processes should all be considered before production begins.

The customer’s downstream operations included LED strip cutting, soldering, adhesive tape application, and winding.

From Equipment Commissioning to Process Investigation

From Installation to Stable Production

The first stage of the project focused on equipment installation and commissioning.

Several practical issues were identified and resolved before the soldering investigation began.

Long PCB Transport

Some 1500 mm boards experienced transport problems in the vacuum reflow system.

The investigation found a mismatch between the machine rail width and the fixture setup. After rail adjustment and fixture correction, the long-board transport was tested successfully.

Vacuum System Verification

The vacuum system was also checked separately.

A one-minute vacuum hold test confirmed that the chamber maintained 0 Bar without pressure decay. This showed that the vacuum system itself was stable and allowed the investigation to move toward process parameters rather than hardware failure.

Other Equipment Issues

The project also included several smaller commissioning problems, including a loose loader power terminal, a sensitive site breaker causing a reflow startup trip, and a placement machine requiring cleaning and lubrication after a long idle period.

These problems were resolved before the main soldering process investigation continued.

The Nine-Day Investigation Into Solder Joint Voiding

Once the equipment was confirmed to be operating normally, the engineering team focused on the solder joint voiding problem.

The customer was using AIM Solder SAC305 NC257-2 solder paste.

1. Reflow Temperature

The initial peak temperature was approximately 245°C.

Although this was within the solder alloy’s melting range, the result was not sufficient to meet the customer’s voiding requirement.

The peak was increased to approximately 253°C, but the improvement was limited.

2. Solder Paste Printing

The customer had originally been applying solder paste manually with a squeegee.

This made paste deposition less consistent.

The process was changed to machine printing using an automatic solder paste printer, allowing the engineering team to control printing conditions more accurately.

Different squeegee pressures were tested. Among the tested conditions, 1.0 kg produced the best result.

3. Flux Volatilization

The next important finding involved flux.

Flux volatilizes at approximately 150–170°C. The engineering team adjusted the thermal profile so that more flux volatilization occurred before the PCB entered the vacuum zone.

Zones 1–5 were adjusted to:

110 / 140 / 150 / 150 / 165°C

This helped reduce the size and number of solder voids.

4. Balancing Temperature and Vacuum

The soldering-zone temperature was then increased to improve the vacuum reflow response.

This reduced voiding further, but the peak temperature reached approximately 265°C, exceeding the customer’s 260°C process ceiling.

The process therefore had to be balanced again.

The final adjustment reduced the peak temperature by 5°C and increased conveyor speed by 100.

The final peak temperature reached 258°C, while the tested solder joint voiding rate was approximately 3%.

The investigation demonstrated that voiding was not controlled by vacuum pressure alone. Solder paste deposition, flux volatilization, thermal profile, vacuum timing, and conveyor speed all interacted with each other.

Why the Vacuum Reflow Process Was the Key

SMT Line for LED Strip Manufacturing in Italy

The investigation showed that the vacuum system itself was not the main problem.

The more important question was what happened before the PCB entered the vacuum zone.

The process had to control:

Solder Paste → Flux Volatilization → Heating → Vacuum Timing → Final Soldering

This is why selecting a SMT vacuum reflow oven should involve more than checking the maximum vacuum pressure.

For LED strip and long-PCB applications, the relationship between board structure, solder paste, heating profile, vacuum timing, and conveyor speed can directly affect solder joint quality.

Training and Production Preparation

While the voiding investigation was underway, I.C.T continued training the customer’s technical team.

Training covered:

  • SMT product programming

  • PCB setup

  • Component library preparation

  • Feeder and nozzle setup

  • Printer operation

  • Reflow parameter adjustment

  • Production changeover

  • Equipment maintenance

  • LED strip assembly

The customer’s engineers practiced using their own products rather than demonstration boards.

The placement stage also required product-specific programming for long PCBs. An advanced flexible SMT pick-and-place machine can be used for applications requiring flexibility across different PCB formats and component arrangements.

By the end of the support period, two customer engineers were able to operate the complete production line independently.

Other Production Configuration Issues Found

The project also revealed several gaps between the customer’s actual production requirements and the original equipment configuration.

The stencil and squeegee dimensions did not fully match the customer’s LED strip products.

The adhesive tape format also required adjustment, while the tape applicator tooling did not initially match the customer’s actual strip width.

These issues highlighted an important lesson for new SMT projects:

Actual product dimensions and downstream materials should be confirmed before equipment shipment.

A production line can be mechanically complete while still requiring additional engineering work before it is fully production-ready.

Final Result: Approximately 3% Voiding

After nine days of controlled testing and 19 parameter combinations, the final tested process achieved:

ItemResult
PCB lengthUp to 1500 mm
Solder pasteAIM SAC305 NC257-2
Final peak temperature258°C
Solder joint voidingApproximately 3%
Vacuum systemVerified stable
Long-board transportSuccessfully corrected
Customer trainingCompleted
Independent operationTwo engineers

The project therefore moved beyond equipment installation and into genuine production process optimization.

The customer received not only a functioning SMT line, but also a more stable reflow process, product-specific programming, practical troubleshooting knowledge, and trained local engineers.

Watch the Italy LED Strip SMT Project

The project included SMT line installation, equipment commissioning, production debugging, and hands-on technical training.

Watch the factory video to see the I.C.T engineering team supporting LED strip production in Italy:

What This Project Teaches LED Strip Manufacturers

This project provides several practical lessons for manufacturers working with LED strips and long PCBs.

  • Verify PCB dimensions and fixture requirements before shipment.

  • Separate equipment faults from process-related problems.

  • Do not treat vacuum pressure as the only variable in vacuum reflow.

  • Control solder paste deposition consistently.

  • Consider flux volatilization when optimizing vacuum timing.

  • Validate stencil, squeegee, tape, and tooling dimensions against the actual product.

  • Use real customer boards during training and production trials.

Hands-On Training for Confident Production

The most important lesson is simple: a production-ready SMT line requires both correctly configured equipment and a process that has been verified on the customer’s actual products.

More Pick and Place Machine Information